Nothing was installed this month. What happens to stored materials?
If you prepare a monthly pay application, a quiet month can still end with a balance on the stored-materials line. Start with the last certified application and track what actually moved on the same schedule-of-values line.
Synthetic example | Glazing package, line 12
Last certified application: $4,000 in stored glass.
This month’s delivery and installation records: $0 newly stored and $0 installed from stock.
Draft pay application: $0 in stored glass.
Expected ending stored balance: $4,000 + $0 − $0 = $4,000. The draft is $4,000 below that check. If $1,500 of the same glass is installed the following month, the stored balance becomes $2,500 and that $1,500 moves into work completed for that period. The move by itself adds nothing to the combined completed-and-stored total.
Keep the prior certified row and the receiving or installation record beside the draft row. If the current status is unknown, flag it for review before treating it as zero. Use your GC’s form and the supporting records it requires.
I work on Jolene.pro. If your records already live in an Excel workbook, one question to try is: Which lines changed in stored materials, and which source cells explain the change?