One ductwork order, counted twice in the forecast
Before you add a superintendent’s estimate to the open purchase orders, ask which orders are already in the estimate.
In a fictional ductwork job, $16,000 has been incurred and $20,000 remains open on a purchase order. The estimate to finish is $25,000, and it already includes that $20,000 order. That leaves $5,000 of uncommitted work. The forecast is $41,000. Adding all $25,000 to the actuals and open order would put $61,000 in the report. All amounts are in USD.
Keep the PO line reference next to the estimate. Check the remaining amount at the same reporting cutoff. If the estimate has no reference or you can’t tell what it includes, flag it for review before subtracting anything. Two amounts can match by chance.
I work on Jolene.pro. Here’s the worked forecast example with the source rows. Where does your team record which purchase orders are already in the estimate?